on 09-29-2006 11:22 AM
Hi experts,
i have a PO with a single service position. The order was correctly transferred to backend system.
Before GR, i modify PO decrementing quantity (so also price), but i receive backend transfer error "price error will become negative - BBP_PD_PO_TRANSFER".
Does anyone know why?
Thanks a lot,
Valerio
1- What is your SRM and ECC release and patch level ?
2-What is the price in the backend PO before you try to change SRM PO ?
3-Are you using inforecord or contract price conditions ?
Kind regards,
Yann
Hi Yann,
1 - Our SRM is SRM 4.00, we have SP9 release.
2 - initial PO qty 674, price 51.150,90
after mod. PO qty 565, price 41.286,20
3 - no inforecords, no contract price. The price was inserted into line position of service item.
Thanks,
Christian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Valem,
1- What is your SRM and ECC release and patch level ?
2-What is the price in the backend PO before you try to change SRM PO ?
3-Are you using inforecord or contract price conditions ?
Kind regards,
Yann
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.