Hi,
Kindly help me on the following:-
My project is closed but some goods are to be recd for PO which was raised before closing .
But I don't want the financial impact on my project , I can allow the cost to be posted to any cost centre but not to WBS.
Second similar thing I want to ensure for any other finacial transaction.
What shud I do, set some user status, TECO or else.
Hi,
Change the PO account assignment WBS to Cost Centre and do the goods posting. Make sure that if reservation created from WBS- Network than you need to close the PO and create new with reference to cost centre.
Enjoy SAP