on 03-09-2012 10:43 AM
Hello experts!
I have created the Implementation project in TCODE solar_preject_admin
TCODE solar_preject_admin -> tab System Landscape -> tab Change Management:
IMG Projects: Green
Change Request Management: Run Check
I have the errors:
Error 1 : Client-specific transport control (CTC=1): No Import single method: No
Error 2 : No consolidation system found for SW0-208 (project ZTEST_DEV)
Error 3 : No track for project ZTEST_DEV with log. system SW0/208
How to eliminate the given errors? I should undertake what actions for this purpose. Thanks!
Hi,
It seems that no Logical Component defined. To use charm you should define log. component
In addition, as a prerequisite of using ChaRM, the client specific
transport control must be activated by setting parameter CTC as 1 for
all managed systems. The transport strategy must also be chosen as
#Single transports#.
Please, check the link below for more information about charm.
Please, let me know if you need further information.
Thanks
Regards,
Vikram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.