I create a project as the follow steps.

I want to allocate it,but I can't because of the message Message no. KD220 and Message no. KD205.

1. create a project.

2.create WBS element.

   wbs level 1.

     wbs level 2.

   wbs level 1.

     wbs level 2.

3.I release these wbs.

4.I change the budget of these wbs by cj30.

5.I change the cost planning of these wbs by cj40

6.I post two good receipt orders by migo which assign to wbs level2.

7.I post two good invoice by miro.

8.I do a post by cj88.

   debit:bs AuC account/credit:pl AuC account

9.I set the settlement rull by cjic.

10.I want to post the project by cj88.

  and it give me some message that I cant post it because of the message below.

Settlement profile 123510 : "Can be settled" -> Enter settlement rule

Can anyone tell me How can I post the project by cj88?

Thanks very much.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

As mentioned above.. steps 8 to 10 are confusing..

Why don't you follow simple process;

1. Maintain the settlement rule from CJ20N to all the WBS marked as account assignment OR to test where you actually posting cost. Select WBS -> Edit -> cost -> settlement rule

2. Run CJ88 for the WBS. Check detail list and execute the transaction (uncheck test mode).

3. Check CJIC report to see settlement postings.

I hope this will give idea where are you going wrong. Please let us know if it helps in resolving your issue.

Pramod

0 Kudos

Hi jie,

   Pls check the settlements of all the WBS.

  

   Regards,

    QIAO

former_member209919
Active Contributor
0 Kudos

Hi Jie,

I think you should open your post in Project System not in PPM.

But really I don't understand your process from 8 to 10. If you settled the project in Cj88 you finish your process. CJIC it is a display report .. very strange,

Regards,