on 03-08-2012 9:20 AM
Hello,
We are using PPDS for planning and scheduling. The planned orders are converted to production orders and sent to R/3. After order release in R/3, user may adjust the quantity and reschedule the order in R/3 to extend the orders when needed. This can be the case for partially confirmed orders also.
But as soon as user reschedules order in R/3 APO overwrites the dates. How can we stop this so that R/3 has the control on orders with REL and PCNF status.
Thanks
PE
Hi,
Can you check the settings defined in /SAPAPO/CP3 for retransfer.
Thanks,
nandha