User exit to replace the cost center during PGI with WBS (OKB9)

Former Member
0 Kudos

Hi Gurus,

During delivery, the WBS element is determined from the sales order that is created with the account assignment as WBS. the WBS element is specified in the sales order.

At the time of PGI, Accounting documents are created with the cost object (cost center) flowing from OKB9 settings instead of the WBS which should have picked from delivery.

can you please suggest any user exit or BADI to pull or replace the Cost center with the WBS element.

thanks in advance

regards

Arun NR

Accepted Solutions (0)

Answers (1)

Answers (1)

eduardo_hinojosa
Active Contributor
0 Kudos

Hi

You can use a FI substitution. See the article [Enhancement of Default Account Assignment (OKB9) |http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/b0eb4e57-c78c-2d10-e0bd-eca8728e7037] by Ajay Maheshwari in this site.

Regards

Eduardo

Former Member
0 Kudos

Hi

the WBS element does not come under the OKB9 settings . our requirement is to get the WBS element delivery instead of the cost center from OKB9 for posting it in the accounting document during PGI

Arun

jpfriends079
Active Contributor
0 Kudos

Just for reference, check whether following SDN thread is help to you:

-

Well, have you given thought to give a try to [OKC9 (CO) |http://wiki.sdn.sap.com/wiki/display/ERPFI/COAccountAssignment].

Also, refer SAP Note 684659 - FAQs about account assignment objects

Regards

JP