How to find for a particular WBS element thourgh which budget has consumed

Former Member
0 Kudos

Hi ,

I have a WBS element C-09864/001/002. In CJ33 system is showing Budget amount 90,000 and distrbuted 90000. So total budget has consumed. Now if i want to know how the budget has consumed ,means in what ways it has consumed like PR or POs and what are those PR& PO doucment numbers.

Apart from PR & PO s directly by posting FI documet also , is there chance for consuming budget .If yes how to find ?

Thanks & regds

ramachadra

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Apart from PR & PO s directly by posting FI documet also , is there chance for consuming budget .If yes how to find ?

-> transaction MIRO, CJ88, KO88

You can use the steps I have provided to check this.

Regards, Gordon

Former Member
0 Kudos

Hello Ramachandra,

In transaction CJ31, please go to menu -> Extras -> Availability control -> Analysis

You can see what is your setting (eg budget profile, tolerance limit, exempt cost element) and of course how/what is contributed to your assigned value and its amount & document number.

Regards, Gordon

Former Member
0 Kudos

Hi,

Distributed doesnt mean budget is utilised - It means budget has been distributed to lower level WBS. Please check report S_ALR_87013558 for budget balance and details.

Regards

Shrikant