Dear experts,

Service engineer will create Trip, gets approval and after coming back he'll enter expenses (T code PR05) and this expenses should hit the project. Is there any link between Travel Management & PS?

Thanks & Regards,

Murthy.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

the account assignment should be a Network with activity or wbs element.

former_member630135
Participant
0 Kudos

And then you need to do PRFC,PRFI,PRRW.That should close the TM-PS cycle.Hope this helps.

jungleem

Former Member
0 Kudos

Thank you.........