CJ708 and CJ009 error in MSP to CJ20N

reena_ghadge
Participant
0 Kudos

Hi,

When i am uploading a project from MSP to CJ20N the error comes

I CJ708 ProjectDefinition Update

Profit center was not created for entire period

E CJ009 ProjectDefinition Update

Start date must be later than "01.01.1980"

Please suggest

Regards,

Reena

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Reena,

It is an information/warning message -> CJ708. The warning is seems correct, Please check the networks start date and end date, if this is not match up with the profit center 'Analysis Period' this warning is prompted.

You can either change the validity of the profit center, in KE52 or change the appointments to your network.

Pertaining error CJ009, the SAP scheduling can only handle a time frame of 60 years. The default setting is from Year 1980 to Year 2048.

You may modify to your system in order change the reference date to -shift- the time frame. This can only be done within the scope of a modification to include program LCXTP000. Please also see SAP note 49257.

Regards, Gordon

Former Member
0 Kudos

hi

check whether the profit center is created or not.

reena_ghadge
Participant
0 Kudos

Hi AP,

The profie centre is already created.

Regards,

Reena

Former Member
0 Kudos

Refer these notes. Might help.

Note 1068507 - PPB : Short Dump on entering a date before 1980.01.01

Note 1071869 - PPB : Short Dump on entering a date before 1980.01.01 - II