on 03-06-2012 4:48 AM
Hello All,
We are having an issue of while executing SNP Heuristics creates a SubContracting PReq only based on Info-Record, but not considering Outline Agreement specified in source lists.
Both the Procurement Relationship and Transportation Lanes exists for Outline Agreement, but still the PReqs are created based on Info-Records, without source location being populated.
Is there any configuration required to create Sub-Contracting PReq's based on Outline Agreement?
Am i missing something, in terms of master data setup?
Thanks,
Mangesh
Hi Mangesh,
SNP subcontracting scenario; as of now, is based on subcontracting purchase inforecords only. If it is just external procurement from vendor, then outline agreements / contract/ purchase inforecord works.
Regds,
Raghav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.