Subcontracting PReq's based on Source Lists (Outline Agreement)

Former Member
0 Kudos

Hello All,

We are having an issue of while executing SNP Heuristics creates a SubContracting PReq only based on Info-Record, but not considering Outline Agreement specified in source lists.

Both the Procurement Relationship and Transportation Lanes exists for Outline Agreement, but still the PReqs are created based on Info-Records, without source location being populated.

Is there any configuration required to create Sub-Contracting PReq's based on Outline Agreement?

Am i missing something, in terms of master data setup?

Thanks,

Mangesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Mangesh,

SNP subcontracting scenario; as of now, is based on subcontracting purchase inforecords only. If it is just external procurement from vendor, then outline agreements / contract/ purchase inforecord works.

Regds,

Raghav