Hi,

I am creating Project via Standard WBS and Network. I have also assigned few materials to this Standard NWP. There are few materials assigned to this std NWP all with Base QTY 1000.

So when i add Execution Factor 10 when creating WBS, i expect system to divide Qty of material assigned on Std NWP by 1000 and then multiply by 10, but system is not dividing the Qty by 1000?

Is there some config i need to do so that Base Qty maintained in Std BOM gets divided by the Qty of material that gets assigned to operative WBS being created?

Regards,

Jatinder

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member183879
Active Contributor
0 Kudos

Hi,

To my knowledge, the execution factor is applicable only for the quantity at either the WBS or network activity level , not for the requirements it generates. I may be wrong.