on 03-05-2012 10:11 AM
Hi Gurus,
As im new to PS module,here i have an issue related uploading composite summary sheet, in this what are the values i should copy from cs sheet to zcjr2 template please help me
Thanks in advance
Regards.
Maran
hi
in CJR2
first you to set the controlling area.
then you have to give the
version no.
from period
to period
fiscal year
either WBS element from -- to ---
or
WBS Element group
Cost element from --- to ---
or Cost element Group
and then values.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Guru,
Thanks,but in zcjr2 template everything is right i.e. versions,from period, to period,fiscal year,wbs elements, what i am asking is what are the values to be tranferred to this cost & cost element in zcjr2 template( i copied this cssheet from zboq to xl file) only thing i am not able to find the exact solution for uploading this cssheet can you please help me in this.
Thanks in advance.
Regards.
Maran
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.