When i assign a stock material to WBS i get a pop up:

CHOOSE:

Reservation for NWP

Reservation for WBS

PR + RES for WBS......

As per standard setting by default system selects "Res for NWP"... i want that by default system should choose option 2 i.e. "Res for WBS" is this possile?

Thanks in advance.

Regards,

Jatinder

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

It is possible with the help of procurement indicator. Please create suitable procurement indicator in OPS8 and assign it to network profile (OPUU)

Regards

Shrikant

Former Member
0 Kudos

Hi Shrikant,

In OPS8, i cannot see any option to make Reservation to WBS default? Can you please share some more details.

Thank you.

Regards,

Jatinder

Former Member
0 Kudos

Hi Jatinder,

Create new entry, then leave 'Control data' section blank. Select default item category as L in bottom. In priorities section, select 1 for project, 2 for plant and 3 for sales order.

Create new project after you assign proc ind. to network profile.

If you have access to IDES system, just check some standard proc indicators created by SAP.

Regards

Shrikant

Former Member
0 Kudos

The settings I told were for Res for WBS. For network just change priority of plant to 1 and project to 2.

Regards

Shrikant

Former Member
0 Kudos

Dear Shrikant,

This is addressed, thank you.