on 03-05-2012 6:48 AM
Dear All,
When i assign a stock material to WBS i get a pop up:
CHOOSE:
Reservation for NWP
Reservation for WBS
PR + RES for WBS......
As per standard setting by default system selects "Res for NWP"... i want that by default system should choose option 2 i.e. "Res for WBS" is this possile?
Thanks in advance.
Regards,
Jatinder
Hi,
It is possible with the help of procurement indicator. Please create suitable procurement indicator in OPS8 and assign it to network profile (OPUU)
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jatinder,
Create new entry, then leave 'Control data' section blank. Select default item category as L in bottom. In priorities section, select 1 for project, 2 for plant and 3 for sales order.
Create new project after you assign proc ind. to network profile.
If you have access to IDES system, just check some standard proc indicators created by SAP.
Regards
Shrikant
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.