on 03-04-2012 9:24 PM
Hello,
Am trying to get the planned cost of 200 maintenance plans in IP31. When i put the range of flocs and execute, its giving me an error. Am not sure why?
1) When i put one floc at a time in IP31, it gives a report of value $164,000.So i thought this is working. But when i put the next floc, it gives the same value...So basically if i put one floc at a time, it gives the same value for all 200 maintenance plans. What is the error here?
2) There is a big difference in dollar value when i press F8 & when i press Display costs in IP31? why is the difference coming?
3) What is the best way to get the Planned cost of Flocs/Maintenance plans in PM? I tried IW38 and that also dont work properly.
Please advice.
Sylvia
i dont find any functional location in the selection screen for IP31. its only plan, category and strategy..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.