I am trying to transfer a BOM to PS which contain a sub bom (assembly). I am not able to explode the assembly, only make

a requisitions.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The sub assembly BOMs which you want to explode, make them as phantom assembly. They will get exploded when you transfer BOM.

Regards,

Mahendra

Former Member
0 Kudos

hi

I tested and it works, but I have then another issue.

I want the phantom to be exploded in another activity, I have set reference point 1702 on the BOM item in the

main BOM and have an activity with the same ref.point, but all is exploded to 1701.

You know how to be able to do this

Thanks

Former Member
0 Kudos

Can you try maintaining different reference point for the children of phantom BOM? It should work.

Regards,

Mahendra

Former Member
0 Kudos

hi

Problem solved and points added.

I have another question, do you know how to mass change the reference points in a BOM