Assigning Stock Material with Backflush Indicator on

Former Member
0 Kudos

Dear All,

I have assigned a Stock material to a PS Activity in the Project, and i expect that when i confirm the activity Material is automatically issued to the WBS?

But on activity confirmation material is not getting issued to the project.

Request you to let me know if there is some config required to make this happen?

Regards,

Jatinder

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I hope the backflush indicator is ticked and material is in stock. Further in OPST tick 'Goods Movement' under Log section. This will guide you to the reason for non issue of material.

Regards

Shrikant

Former Member
0 Kudos

Hi Shrikant,

Yes the backflush indicator is ticked and material is in stock (unrestricted stock for the WBS is available). Also in OPST Goods Movement tick is selected.

Still on confirmation material is not getting issued to the WBS?

Warm Regards,

Jatinder

Former Member
0 Kudos

Please try transaction CN25 for confirmation of activity. Do not confirm it from project builder or CJ20N.

Also in CN25, confirmation parameters maintain flag for 'all items'.

Regards,

Mahendra

Answers (0)