Dear Expert ;

I am assign the Coding MAsk same As Below:

D /XXXX/0000/0000/0000

I want the setting same as below.

PD : NP/CT01/0001

WBS1 :NP/CT01/0001 - Level 1

WBS2 : NP/CT01/0001/0001: - level 2

but Presentally system provide

NP/CT01/0001 - Level 1

NP/CT01/00011- Level 2

Plz. Suggest the Setting with proper Flow.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi mmayoor123,

Please maintain projec id: D

Coding mask : /XXXX/0000/0000/0000

Then it will create as disired wbs coding.

srikanth

Former Member
0 Kudos

Thanks For Quick Reply and Suggestion, Matter resolve.

Former Member
0 Kudos

You have defined coding mask as D /XXXX/0000/0000/0000 and you are creating a project with the nomenclature as NP/CT01/0001.

The project id that you have mentioned in the coding mask is D and you are creating a project with the project id as NP. System is behaving as designed. Try creating a coding mask with the project id as NP and then test.

Check and revert.