Hi all,

We are on SRM 7.1 ECS.

I have some questions regarding the commitmemt posting and release for SRM PO's which are replicated to ECC:

1.For all material PO's if the GR is done on ECC,at that time is the commitment released automatically?Is the trigger point for the release of commitments the GR posting in ECC?

2.For material PO's,after they are replicated to ECC, if the SRM PO is changed to rmeove the GR indicators,and then the invoice is posted for the PO's in ECC,should the commitments for the PO lines be released or no?

3.For all service/Limit PO's,if there is no SES in ECC and only invoice posting done,than how are the commitments released for the service lines?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member208675
Active Contributor
0 Kudos

Hi,

Refer to SAP Note 828231 - Commitments and SRM

It will resolve your first 2 doubts.

Regards,

yaniVy