Planned capacity not integrated to Bucket

Former Member
0 Kudos

Hi Experts,

We are working with PPM 5.0 and facing the following scenario:

We have defined an scenario where the item gets the planned capacity from the role demand in the project management system (item process = Integration) and the bucket should roll up that information (bucket process = roll up).

We are getting the integrated information in the item correclty, but when we go to the bucket capacity management, the planned capacity appears as 0. If we include subobjects we can see the correct demand assigned to the item.

For the integration we are running program /RPM/CAP_PLAN_INT

If instead of the integrated value we look at the forecasted which is manual at item level and rolled up at bucket level, the roll up is executed correctly.

Has any of you faced that issue? Are we missing any step to get the rolled up information? Is there any SAP note on this?

Thanks in advance.

Best regards,

Neil

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Missing the execution of program /RPM/BUCKET_ROLLUP