Scheduling Agreement Output type

Former Member
0 Kudos

Hi, I have a Scenario Where I need to trigger an output(Idoc) filtering by plant to a third party system.

When I checked we have plant at Item level for the sales document. But the Output type needs to trigger at Header level. How can I do that.?

Any valuable suggestions would be helpful.

Regrards,

Daphne.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184701
Active Contributor
0 Kudos

you need to use another output type.

what is the type of your shed. agreement and what output type you try to use?

Former Member
0 Kudos

Yes Its LP Type. Yes we had a new output type but I need to filter the Sales Documents by plant.

Consider Example:

We have Scheduling Agreement with various line items. We will not have different plants in the item level even though it allows. If we have 3 line items we have same plant for all the line items from which these products are being delivered.

former_member184701
Active Contributor
0 Kudos

i recommend you to create a new output type copying from the standard LP00

in V/30 for your new output type

goto general data and look at Access sequence you use there (set up a new one if you need).

run VV12 and make sure the output condition record exists and valid and all settings are correct !

create a new shed. agreement (use your new output type) and test it.

regards,

former_member303858
Contributor
0 Kudos

HI,,

Check and let us know that if the plants at header level and item level are same or different..

SB

Former Member
0 Kudos

Satish - We do not have Plant at Header level in the Scheduling Agreement.