on 02-28-2012 1:59 PM
Hi All,
I need to find out the total man hours worked in a timeline in Plant Maintenance. Can some one please let me know as to how we can do this?
Thanks in advance for your help,
Kanthi.
HI you can get plan & actual activity(manhour) in report S_ALR_87011777 - Activity Type: Load
shakti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Greetings Kanthi,
IW47 will give you the hours of actual work that have been Confirmed against PM orders
Or if you have a process where you don't confirm hours manually, try Planned hours for Operations in IW37N
Also http://forums.sdn.sap.com/thread.jspa?threadID=2014538&tstart=0
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.