Total Man Hours worked

Former Member
0 Kudos

Hi All,

I need to find out the total man hours worked in a timeline in Plant Maintenance. Can some one please let me know as to how we can do this?

Thanks in advance for your help,

Kanthi.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member385375
Contributor
0 Kudos

HI you can get plan & actual activity(manhour) in report S_ALR_87011777 - Activity Type: Load

shakti

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Kanthi,

IW47 will give you the hours of actual work that have been Confirmed against PM orders

Or if you have a process where you don't confirm hours manually, try Planned hours for Operations in IW37N

Also http://forums.sdn.sap.com/thread.jspa?threadID=2014538&tstart=0