make to order production - schedule line not confirmed

Former Member
0 Kudos

Hi,

I created a " make to order production " having few normal materials & few supersession materials.

created PO, GR,invoice, all done.PO is updated in sales order.

Schedule line is automatically confirmed for normal materials, but not confirmed for supersession materials.

can anybody tell me , how schedule line can be automatically confirm for supersession materials.

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Is your scenario a third party one? After you finished GR for the PO, have you checked inventory of those materials? But I still didn't understand what's difference between new material and "supersession" old one? New for what and old for what? Could you be more specific or any example will be helpful.

Former Member
0 Kudos

Here both material are same , substitution reason 009(parts change)

item 10 (X) itcg TAPA

item 11 (X) itag TAB

Former Member
0 Kudos

Looked like it is a APO material, for APO, one item is not to be confirmed, please try to create an outbound delivery to see if it works.

Former Member
0 Kudos

schedule line is getting confirmed manually, delivery is also possible.

but we have more than 1000 materials , we can not confirm schedule line manually , it will take a lot of time.

Former Member
0 Kudos

What does "supersession" material mean here?

Former Member
0 Kudos

new material replacing old material