I have planned some values for my external activity (via PR), and my question is- when I am fetching some costs repost (S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned), I am able to see the planned values for my activity (even I checked it via CJ20N also). But, when I am checking the same in CJI5 report, I did not see any values there, what could be the reason? I guess, PR is a commitment and that should have displayed in CJI5, but, why it did not? Please let me know.
Thanks,
Regards,
Sumanth
Hi,
Check in OKKP whether Commitment Management is active for relevant Controlling year for the said Financial Year.
You can also run report RKANBU01 for correcting commitment values.
Thanks,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sumanth,
1.Please enter OKKP t-code, select controlling area and double click on u201CActivate component/control indicators u201C under basic data. And now check u2018Components activeu2019 for commit management.
2.Go to T-code SE38 and enter program name u201CRKANBU01 u201C execute for your project.
Rgd
srikanth
How is the PR created? Is it by way of attaching material component directly to an activity and generating a PR or is it created by running MRP. If its created by way of MRP run then system does not consider this as a commitment.
Other points that need to be checked are mentioned in the post above. Check and confirm.
Other thing that you can do is check if the commitment value is seen in the table COOI. Depending on which object you have raised the PR on you will have to mention the object number accordingly in COOI table. If its against a WBS get the OBJNR from PRPS and if its for an activity get the OBJNR from the AFVC table.
Check this and revert.
Hi Gokul,
I need your help in checking the COOI & AUFK table. This is because, i tried to check the same, but i m confused there.
I am not able to point out the object number (OBJNR) for my Activity for which the PR was created. I went to AFVC table and I had selected the OBJNR field from the selection, it displayed their in the table, but, I am not able to select the field name for my Activity... please let me know how to select the field name for my activity in the AFVC table? Also, let me know do I need to give the Activity number also (like 0010, 0020 etc)?
And, FYI - the PR was created by attaching the material component directly to my activity. No MRP plan was done. Also, i have 2 activities, 1 internal, 1 external, and both have PR generated against to them.
Regards,
Sumanth.
Hi sumanth,
Please check whether the stock g/l for material component, which is assigned to your external activity is created as statistical cost element or not. if not create particular stock g/l as statistical cost element, then only System will check Budget and availability control.
Please ask your CO consultant to create statistical cost element of category 90 for that particular G/L account.
Regards
srikanth
Hi,
I hope you are entering correct dates on selection screen. Further click on 'Change DB Profile button' (CtrlShiftF3) at the top and check whether related objects (network, activity) are ticked.
Also check if any filters or dynamic selection is set.
Regards
Shrikant
Edited by: Shrikant Rakate on Feb 29, 2012 2:17 PM
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.