on 02-27-2012 7:55 AM
Hi,
I need to map a scenario where some material required for the project execution, will directly be supplied at Project site.
This material will be directly procured only for Project.
I want to understand how do we deal/map such scenario in PS.
Warm Regards,
Jatinder
Hi,
Create 1 storage location for all these kind of projects. Assign material to Project and purchase with PR + Reser against WBS element.
So PR will be AA as Q which is special stock indicator. Take GRN virtually at site. So you can see materials also at the site.
Regards
Keshav