Material Procurement for Project

Former Member
0 Kudos

Hi,

I need to map a scenario where some material required for the project execution, will directly be supplied at Project site.

This material will be directly procured only for Project.

I want to understand how do we deal/map such scenario in PS.

Warm Regards,

Jatinder

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Create 1 storage location for all these kind of projects. Assign material to Project and purchase with PR + Reser against WBS element.

So PR will be AA as Q which is special stock indicator. Take GRN virtually at site. So you can see materials also at the site.

Regards

Keshav