Hi,

I have uploaded a project from MSP to PS at the end project upload sucessful message appears but there is no change in PS i.e no new activites are getting created in cj20n.

Regards,

Reena

Accepted Solutions (0)

Answers (3)

Answers (3)

wajdi_saif
Discoverer
0 Kudos

Hi,

Ttry to check on BAPI_Transaction_Commit

which commits the created objects in the database.

thank you,

wajdi

Former Member
0 Kudos

Hi Reena,

Please check 'retain ps' column in msp, that field should be "yes" while uploading to sap ps.

Srikanth

reena_ghadge
Participant
0 Kudos

Hi,

The retain PS column has yes

Regards,

Reena

reena_ghadge
Participant
0 Kudos

Hello,

Any updates.

Regards,

Reena

reena_ghadge
Participant
0 Kudos

Hi,

Any help .

Regards,