cancel
Showing results for 
Search instead for 
Did you mean: 

Compare Components Quantity in different Versions

Former Member
0 Kudos

Hello Experts,

We are using networks in our projects.

We create simulation versions using CJV4.

We would like to compare diferent versions but not only at cost level, also the material quantities.

Is there any report available?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Why don't you explore the functionality of Project Versions? You can then compare the versions in CN41N.

Former Member
0 Kudos

I already knew report CN41N, but I have added all the columns and I can stil not see the material requirement quantity.

Is there any other report or way of comparing materials requirement quantity between versiones?

Thanks

Edited by: balfor on Feb 28, 2012 9:08 AM