PO confirmation not sent to ECC

Former Member
0 Kudos

Hi SNC Gurus

I have typical problem in PO collaboration, for PO confirmation. The PO is confirmed and published in SNC and showing status published, but the confirmation not updated on ECC side.

In application log (Transaction SLG1 - getting error as- PO XXX Item XXX: "ShippingPeriodEndDateTime should come before ShippingPeriodStartDateTime"

One more thing I checked is when PO delivry date is as per "Planned delivery date" in the material master then PO confirmation is working fine.

But when PO delivery date is not as per planned delivery time . ie suppose planned delivery time is 15 days in matl master but i enter delivery date in PO as equal to future 10 days then PO confirmation is not flowing from SNC to ECC..

Also please let me know how mode of transport duration in transportation lane affects PO shipping date on SNC side?

Will appriciate you early reply.

Thanks

VSK

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi VSK,

Go to SPRO>Supply Network Collaboration>Basic Settings>Validation>Own Settings-->Maintain Settings in Validation Profiles

Maintained below settings:

Val.profile:POC3

Validation check:PO_ACCEPTED_CONF_PUBLISH

Check stat:Inactive

Save this setting and check.

Regards,

Nikhil

Former Member
0 Kudos

Hi Nikhil

Thanks for the reply, but in POC3 we have only below validation profiles maintained

POC3 PO_COMPONENT_PRODUCT_INVALID A Active

POC3 PO_COMPONENT_PRODUCT_MISSING A Active

POC3 PO_COMPONENT_QUANTITY_MISSING A Active

POC3 PO_COMPONENT_UOM_INVALID A Active

POC3 PO_COMPONENT_UOM_MISSING A Active

The profile you mentioned is not maintained.

Thanks

VSK

Former Member
0 Kudos

Hi VSK,

In path which i have mentioned to save the settings in that we maintained as per customization.

As per the need we maintained the validation settings here you can maintained any junk value also system does not checks.

So if it is not maintained then maintained and check.

Regards,

Nikhil

Former Member
0 Kudos

Hi

There is validation profile for this in SNC SPRO. By default it is active if you deactivate that you will not get this error and confirmations will be sent to ECC.

Thanks

Pravin