Hi,

Can we copy Material BOM directly to any Activity in a Project?

When i try to do this i get the option Explode BOM as greyed out for me? Can someone explain why is this greyed out for me?

Thanks in advance.

Warm Regards,

Jatinder Bansal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Yes it is possible to copy Material BOM to an activity. There are certain prerequisites to be met before you do this. You need to maintain reference points in the activity and the BOM items. Tcode CN33 is used to transfer the BOM to an activity.

Go through SAP Help to understand more on this.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can following options:

1. Perform BOM transfer - Search in forum or help.sap about this functionality

2. Add BOM header material in project and then perform explode BOM function. This function is greyed out for non-header materials.

Let us know if this helps.