on 02-22-2012 4:19 PM
Hello Experts,
Please share your thoughts on the System Status "UD ICCO SPCO ORRQ". Not sure on why the Lot getting the status ORRQ "Order record required"
What is the Condition in which the system triggers this Status? how to complete the inspection processing once we get this status? Is it a Particular Configuration setting that expects a Process Order Record?
Appreciate your quick response.
Regards
Raja
Edited by: rajatamil on Feb 22, 2012 5:19 PM
The ORRQ is related to the production side. Until the order record is created, you will not be able to archive off the inspection lot. The order record is required because it was required by the production order that caused the inspection lot to be created. I.E. your production folks still have some work to be done.
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
UD- Usage decision made
ICCO- All inspection completed
RREC- Result confirmed
SPCO-Stock posting completed
I think afetr UD there is nothing to be done from QA side. Will you tell about the detail process, I mean what inspection lot origin you have used etc
Shakti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.