Hi All,
I am getting a settlement issue (settlement from WBS to CWIP) for a specific WBS while doing the Project settlement in collective. The error message is given below:
Complete allocation structure A1
Message no. KD503
Diagnosis
During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
Cost element 40100901 cannot be assigned to a settlement cost assignment in allocation structure A1, and therefore it cannot be assigned to a settlement cost element.
Please help me
Regards
Rofique
Hi,
At the first instance i feel that you are using a cost element of the incorrect cost element category. Check the other cost elements in the Allocation Structure and compare them with the one mentioned in the error details. See if the cost element category is different.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the allocation structure A1 assignments, to the assignments whether this cost element is assigned in source or not. Source can be a range of cost elements or you can assign a cost element group also in source, if you are using cost element group assign this cost element to that group or assign this cost element in one of the assignements source of the allocation structure, this will solve your problem.
Also alternatively as Mr Nithin suggested change the allocation structure A1 to A3 at network activity settlement parameters, but ensure that the cost elements is in A3 allocation structure or else you will get same error like for A1.
thanks
regards
kishore