Hi,

I am assigning Internal Activity to the NWP, with a specific workcenter for which hourly rate is defined in KP26.

So i expect that when i select this activity and go to Edit --> Cost --> Planned Actual --> Activity/Element i should get the planned cost in the output, But i am getting an error "Network does not have activity account assignment".

I am able to see this cost when i check on Network using CJ20N,

Can someone help me understand how can the cost be shown at Activity level

Thanks in advance.

Warm Regards,

Jatinder

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Please close/mark answered the thread if issue is resolved.

Regards

Shrikant

Former Member
0 Kudos

Dear Shrikant, Gokul,

Thanks a ton for all your inputs to my queries in last few days.

Warm Regards,

Jatinder Bansal

Answers (2)

Answers (2)

Former Member
0 Kudos

Shrikant has rightly pointed out the cause of the issue. In tcode OPUV check whether you have ticked the box for "ActvtyAcctAsgn" for the specified plant and Network Type combination. If it is not ticked system treats it as a header assigned network and all the costs will be shown at the network level and not at the activity level.

Read SAP Help for more information on this.

Former Member
0 Kudos

Hi,

You are using header assigned network so cost will come directly in network. If you want cost in activity, use activity assigned network.

Basically you need to use network type for which parameters activity assigned is used.

Regards

Shrikant