on 02-21-2012 2:25 PM
Dear Gurus,
Can anyone please describe the procedure that are required for performing Stability Study.
When I create initial inspection lot, its status is created. When I go for sample size calculation, Flexible Selection and Changing of Specifications is shown, what is this?
Please Elaborate, Thanks in advance
Hi,
Please go through the below links.
http://help.sap.com/bp_bblibrary/600/HTML/P42_EN_DE.htm
http://help.sap.com/bp_pharmav1600/Pharma_DE/HTML/P56_Scen_EN_DE.htm
http://forums.sdn.sap.com/thread.jspa?threadID=1319980
If the inspection lot is created status means you have to create inspection plan
Regards
Hari
Edited by: Harikris_83 on Feb 21, 2012 10:09 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Create inspection plan with proper usage, assigned it with ur sampling lot Via QA02.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.