Hi Gurus,

i have created project with wbs and i am able to save.after adding network, activity and tried to save.than it is giving run time error also not allowing to save.After debugging abaper told me that problem is with: MATNR IS UNCLEAR:

Please help me

thank you

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi

check out this sap note

1347823 MRS: RUN TIME ERROR "RAISE_EXCEPTION" in CJ20N AND CN22 02

Former Member
0 Kudos

Hi,

If its a short dump, contact your basis team, they should be able to help you. Also, i hope u tried options like Log-off, restart of your system. I also hope, u have all the authorizations to create a project in your system.

I dont feel the problem is with material plan for your activity. please check once again with your developer.

Regards,