How to carry out the Finite Scheduling

Former Member
0 Kudos

Dear Sir,

We are in manufacturing of industrial machine and MRP run is against the WBS account assignment (MD51) . The FERT item has multi-level BOM and after MRP run for a FERT (having project dependent requirement) , we have multiple planned orders generated and these planned orders have wbs account assignment .

At any time there are apparox 20 different projects in manufacturing , it means we have planned orders for almost 20 different WBS accounts .

MRP execution is being done in R3 and generated planned orders are CIF to APO .

After CIF of planned orders , we execute FIX-PEGGING heuristic so that planned gets linked with their dependent requirement (i.e ultimately with project generated requirement) .

We are required to Finitely schedule these planned orders in PPDS and during scheduling FIX-PEGGING relation should be maintained (means an Order which is dependent on a higher level Order requirement, should be scheduled first ) .

We request you to kindly guide us as what steps need to be followed for Finitely Scheduling these Networked Orders ( i.e Orders having a FIX-PEGGING relationship) .

With thanks & Rgds

Sonia

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member583456
Active Participant
0 Kudos

Hi Sonia,

please have a look at the Enhanced Backward Scheduling Heuristic SAP_DS_02 .

Best regards

Thomas