on 02-20-2012 12:10 PM
Hello,
Please help me in uderstanding the relation between CJ40 and Cost elements.
I am trying to plan one of my WBS element in using CJ40, when put some value for the same WBS element and click on u2018primary costsu2019 tab, it took me u2018planning primary costs-overview screenu2019 (there it displayed a list of cost elements), so here, I wanted to know-
1. How does cost elements displayed there, I mean, where does the setting has maintained? So that they are displaying in CJ40?
2. I have 2 internal activities in the same WBS elements, can I plan for the same in CJ40 (rather than planning costs using materials and work centers for the same activities)?
3. If I plan cost for WBS, and while posting costs, if I account assign my network and activity, would system allow it?
Thanks for your time and understanding.
Regards,
Sumanth
Hi,
1. Cost elements are coming from the the primary cost element group defined in planning profile in OPSB.
2. no
3. yes
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Harsh,
Thanks for your response. It really makes a sence.
Just need an quick clarification from your end, when we plan activity (especially Intennal), we release and plan costs and then go for execution, so here, RELEASE was the initiator for the operation.
But, I wanted to know- what exactly meant by CONFIRMING an activity? What is its importance? And what are its limitations /scope?
Thanks again for your time and understanding.
Regards,
Sumanth
Hi,
But, I wanted to know- what exactly meant by CONFIRMING an activity? What is its importance? And what are its limitations /scope?
Confirmations document the state of processing for activities and activity elements in a network.
When you post confirmation actual costs from Activity are posted.Actual Dates are updated to Network
You control the following business functions via confirmations:
Reduction of work center capacity load
Update of the actual costs based on the confirmed data
Update of network data, such as duration, work, and status
Update of dates for WBS elements
Copy actual dates to milestone (depending on degree of progress)
Removal of the billing block in the billing plan
Backflushing and unplanned withdrawals of material components
Posting of open reservations
Activation of milestone functions
Triggering of workflow processes when there are discrepancies in the confirmation
You can check http://help.sap.com/saphelp_47x200/helpdata/en/8e/b9853488601e33e10000009b38f83b/frameset.htm for more information.
Thanks,
Nitin
Hi,
First you plan, then for execution you release activity. When you release activity several business transactions can be perfomed on that activity. For details on business transaction click on th 'i' button besides the activity statuses.
Confirmation simply means activity is completed partiall(some percentage) or fully. Nitin already provided all important details regarding confirmations.
Regards,
Harsh.
Hi Nitin/ Harsh,
Thanks for your responses.
I understood that confirmation states the completion of work interms of percentage or full, and we can plan and control many business functions via the same. But, once I confirm an activity, would it be possible to again plan some cost/plan work for the same activity? Also, the status Confirm can be revoked?
Regards,
Sumanth.
Hi,
Does somebody know how to do in CJ40 for secondary cost element planning are possible?
To date, there is only primary cost button is enabled.
Regards
Thu-Huong
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.