Commitment for Reserve for Network!

Former Member
0 Kudos

Dear Experts,

When I assigned stock-item material component to activity, I choose "Reserve for Network".

When I run MRP for that material, although PR is generated but the commitment not increase in report S_ALR_87013533

for that activity (and the corresponding WBS element as well)!!

Is it the standard behaviour of system?

Please advise.

Thanks and best regards,

Khoa Huynh

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

this is standard behavior. PR generated through MRP wont increase the commitment.

Former Member
0 Kudos

Thanks Abdul Khader.