cost by period on activity

former_member216702
Active Participant
0 Kudos

Hello,

Is it possible to affect period activity manually?

I want to create a distribution key wich can let the user put the work H by period.

Thank you

Thierry

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

With Standard you can plan cost by period using distribution key in KP26.

The same cost planned for that period is considered for calculation when we enter hours in that particular date.

But , distribution key for entering hours in standard might not be possible. Let us wait for others to comment.

Thanks,

Nitin

former_member216702
Active Participant
0 Kudos

hello,

thank you for your response.

If i understood, is not possible with activity to do the same think as CJ40 ?

Do you think is good to do a specific program wich update table directly (as CJ20N when we re calculate cost) ?

Thank you

Thierry

Former Member
0 Kudos

Hi,

If i understood, is not possible with activity to do the same think as CJ40 ?

Yes, you are right. Planning done for CJ40 to which you are refering is the Cost Element based period wise planning and not available for Networks .

Please check this link http://help.sap.com/saphelp_47x200/helpdata/en/4c/226d8d46e611d189470000e829fbbd/content.htm

Do you think is good to do a specific program wich update table directly (as CJ20N when we re calculate cost) ?

I am not able to clearly identify your requirement from this. Also there are many things available in standard.

Thanks,

Nitin

former_member216702
Active Participant
0 Kudos

Hello nitin,

Thanks a lot four help.

I close the thread.

Thierry