Dear Experts

I would like to change loading date in outbound delivery.

we have requirement from our client that he wants to manually change loading date in delivery.

for ex-

as per existing system configuration system shows following data.

if customer requested delivery date is say 20 Feb then system does calculation and propose

pick/pack date- 20 Feb

loading date- 20 Feb

goods issue date-20 Feb

delivery date- 20 feb.

please suggest what we can do to get the desired solution.

Thanks in Advance.

Regards-

Hitesh

Accepted Solutions (0)

Answers (1)

Answers (1)

prasanna_kumar4
Active Contributor
0 Kudos

Hi

Check shipping point

SPRO>Enterprise Structure>Definition>Logistics Execution>Define, copy, delete, check shipping point

Determine Loading time Mention SPACE (Remove C) and check

Try once because i never tried

Regards,

Prasanna

hiteshv_talele
Participant
0 Kudos

Hi ,

Thanks for your reply.

Can you please tell me if i change loading date in delivery manually , then what effects it have on delivery process means does it affect availability or any module integration.

Thanks.

prasanna_kumar4
Active Contributor
0 Kudos

HI

As per my knowledge it will consider the loading time at the time of availability check

For better Understand about the Availability check , check the below link

[Available to Promise (ATP)|http://wiki.sdn.sap.com/wiki/display/ERPLO/AvailabletoPromise+(ATP)]

Regards,

Prasanna