on 02-17-2012 9:46 AM
Hi,
I am using collective PR functionality in projects. When I upload the material from external Excel sheet and transfer the BOM, single PR is getting created in the system, however the item nos in PR are not identical with the sr. nos. given in excel sheet. If you have any information on this please share.
KPG
Hello,
It depends on item number of the activity to which material is assigned.
Reg
Keshav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Did you give the WBS elements the materials should be assigned to in the excel. If you have given WBS there then the items in the PR will be according to the WBS I think. Any please verify.
Regards
Sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.