PS...Collective PR indicator Functionality

Former Member
0 Kudos

Hi,

I am using collective PR functionality in projects. When I upload the material from external Excel sheet and transfer the BOM, single PR is getting created in the system, however the item nos in PR are not identical with the sr. nos. given in excel sheet. If you have any information on this please share.

KPG

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

It depends on item number of the activity to which material is assigned.

Reg

Keshav

Former Member
0 Kudos

Hi

Did you give the WBS elements the materials should be assigned to in the excel. If you have given WBS there then the items in the PR will be according to the WBS I think. Any please verify.

Regards

Sagar

Former Member
0 Kudos

Hi,

yes I do mention the WBS element along with activity ID to whiche the material need to assign.