Confirming Activities in specific order

Former Member
0 Kudos

Hi,

Is there any way to setup the system that system does not allow me to confirm activity 20 till activity 10 is confirmed.

I tried with Milestone functions but seems that it is not the solution to achieve this function.

Warm Regards,

Jatinder Bansal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Custom code can be written in activity confirmation exit to check whether earlier activities are confirmed. Check exits CONFPS01 to CONFPS05 to see which is most suitable.

Regards

Shrikant

Former Member
0 Kudos

Hi Shrikant,

Thank you for the so swift response.

I dont want to go vis developement route, is there any config setting/User status/Milestone function etc to achieve this.

Warm Regards,

Jatinder Bansal

Former Member
0 Kudos

Hi Jatinder,

As per my knowledge configuration is available to release multiple activities (Milestone functions) and not for blocking release. The development which I have suggested is low - medium complex, so suggest to consider it.

Regards

Shrikant

Former Member
0 Kudos

Hi

I am not sure you can contorl such functionalities throgh configuaration. Because ot that reason, we use User exits to control business functions in defined way.

Hope this make sense and let us know if you still have questions.

Regards,

PSR

Edited by: PSR on Feb 20, 2012 5:49 PM