on 02-17-2012 9:35 AM
Hi,
Is there any way to setup the system that system does not allow me to confirm activity 20 till activity 10 is confirmed.
I tried with Milestone functions but seems that it is not the solution to achieve this function.
Warm Regards,
Jatinder Bansal
Hi,
Custom code can be written in activity confirmation exit to check whether earlier activities are confirmed. Check exits CONFPS01 to CONFPS05 to see which is most suitable.
Regards
Shrikant