on 02-17-2012 9:01 AM
Hello experts,
we have the following problem in cProjects 4.5. We have in our projects some tasks below the project definition. This tasks are not visible at the tasks dashboard, after releasing. We can only see released tasks below from phases in the task dashboard.
Does anybody know this problem and have a solution?
Thanks in advance.
Regards
Christian
Hi Christian,
Please implement SAP Note 1559728 - Task dashboard: Some tasks are not displayed.
BR
Matthias