cProjects 4.5: display tasks under project definition in Tasks dashboard

Former Member
0 Kudos

Hello experts,

we have the following problem in cProjects 4.5. We have in our projects some tasks below the project definition. This tasks are not visible at the tasks dashboard, after releasing. We can only see released tasks below from phases in the task dashboard.

Does anybody know this problem and have a solution?

Thanks in advance.

Regards

Christian

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Christian,

Please implement SAP Note 1559728 - Task dashboard: Some tasks are not displayed.

BR

Matthias

Former Member
0 Kudos

Hi Matthias,

thanks for this hint.

regards

Christian