We have setup the PROXY setup between the PI and SAP system , the file is being picked up and converted into Proxy and send to SAP.
We are getting success (Checked flag) in PI SXMB_MONI which shows the message is successfully sent from PI but the messages in SXMB_MONI in SAP is showing Scheduled (green flag) . Hence SAP is not receiving message , please help in proving what can be missing from the setting point of view or what is missing ?
Hi,
>>>Hence SAP is not receiving message , please help in proving what can be missing from the setting point of view or what is missing ?
you forgot to register the queues in ERP in - SXMB_ADM - register queues link
Regards,
Michal Krawczyk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
easy... yuo have two solutions:
1. go in SMQ2 of ECC, and start manually (F6) each line, everytime for all your future exchanges
2. or go in SMQR of ECC and register the queues. When the queue is registered, then queue entries are automatically processed...
personally I prefer the 2nd solution !!
Regards.
Mickael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.