on 02-15-2012 12:36 PM
Hi,
When I am creating the PM order for Stock item, I am getting these error messge.Error when calculating costs see log like:
Messages were issued when costs were calculated (see log)
Message no. CK262
and also iam not getting planned cost .in the pm order.
In Material Available check confirmation proposal id done in that my required stack item 5,
apart from that it's shows material no;xx and open quantity 5 for EACH
but Confirm Quality is 0, after I am saved the order, system says" error in cost calculations see log.
Forcefully I am saving the order, then system not display any cost of the stock material, it's says only operation cost only.
From where we came to know that stock item cost in Order, kindly advise me your valuable inputs to me
Thanks
by
bujji
Define scope of check as follow
SPRO PM&CSMaintenance and Service ProcessingMaintenance Service OrdersFunctions and settings for Order types Availability check for materials ,PRTs and CapacitiesDefine scope of check
then use availability check 1- check availability during irder creation
Also check the price of material in costing view of material master MM03
If no price is there maintain price MR21
Shakti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinu
Thanq for you reply
I checked avilability check 01 and material linked in Pm Scope of check & order
but in Check of the logs >cost determination in IW32--> below error came
Consumption account cannot be determined
Message no. CK322
Diagnosis
Automatic account determination could not find a consumption account with the following criteria:
Chart of accounts : 1000
Transaction : GBB
Valuation/acct modification : /VBR
Material/valuation class : 000000000007000000 /3040
Procedure
Check the Customizing settings for account determination.
so kindly suggest me for the above
Thanks
by
bujji
hi
pls check the below
-Check the logs >cost determination in IW32
-Check any price maintained for material master in MM02
-Check the availablity check 01 or 02 for the material which will be linked with PM scope of check and order type
Regards
Seenu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.