We are using SRM 7.0 Extended classic,have Org structure in SRM which is in sync with ECC.Now in one of our training system during client refresh has lost all Org structure related data in ECC.My questions follows,

1)Do i need to again Org structure in ECC and then PFAL to SRM or any client copy from Dec would do the thing,Considering Dev as a standard one which we have all data.

2) SRM client has not been refreshed,if we do org structure in ECC and then if we move to SRM,does it over write the data.

Regards,

Naveen.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member208675
Active Contributor
0 Kudos

Hi,

1) Any copy would do. You don't need to create org structure in ECC.

2) Yes. Org Structure transfer from ECC to SRM will overwrite data.

P.S I assumed ECC org structure as HR org structure