on 02-14-2012 1:16 PM
Dear Friend's,
Here I have a requirement of, to execute standard report S_ALR_87013558 (Budget/Actual/Commitment/Rem Plan/Assigned) in background processing mode. Here we have to run this report in background on daily basis at a particular given time.
Once this report gets executed in background, output of this report should get converted automatically into txt file and this converted txt file must be downloaded in a respective folder automatically by giving desired path.
After completion of this process, downloaded txt file they have to use for internal MIS reporting purpose.
Is this possible via standard PS or else I have to go for the development.Please suggest, what should be the approach?
Regards,
Sandeep
Hi Sandeep,
Check if you can create batch job to run for S_ALR_87013558 using SM36
The Program name is GP8YTY7TBR1TYRPCIPKAC6X9GZG
Please check with ABAP.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.