on 02-14-2012 6:11 AM
hi,
greetings.
hi have strucked in one place.
we are running back ground job scheduling for both time basd maintanace and performance based maintance.
it was generating good for all
un fortunately system stopped generating it is keeping hold even then call dates is completed
call no plan date call date completion duepackage scheduling type/status active version unit
9 10.12.2011 10.12.2011 WK Scheduled Complete 0 Da
10 17.12.2011 17.12.2011 WK Scheduled Complete 0 Da
11 24.12.2011 24.12.2011 WK Scheduled Complete 0 Da
12 31.12.2011 31.12.2011 WK 1M Scheduled Complete 0 Da
13 07.01.2012 07.01.2012 WK Scheduled Complete 0 Da
14 14.01.2012 14.01.2012 WK Scheduled Complete 0 Da
15 21.01.2012 21.01.2012 WK Scheduled Complete 0 Da
16 28.01.2012 27.01.2012 WK 1M Scheduled Hold
17 04.02.2012 03.02.2012 WK Scheduled Hold
18 11.02.2012 10.02.2012 WK Scheduled Hold
19 18.02.2012 17.02.2012 WK Scheduled Hold
20 25.02.2012 24.02.2012 WK 1M Scheduled Hold
plz suggest us in the t-code of sm37 when we checkd with basis team its getting releasd ,and finshed with spool request
and no errors also.
after reschedulnig also its not getting scheduled for completed dates.
Hi,Divakar
you might have removed sort field or Authorization group field in maintenance plan additional data tab.
Please check once.
Regards,
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
it appears, for some reason that system is not recognizing that the previous order is completed. pl check whether the completion confirmations are done in iw42 .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.