on 02-13-2012 6:39 PM
Dear all
It's possible to change the network profile when copying a project?
We are using a complete Project as a template. We now have created a huge project template with a lot of relationships. Now we want to create a new template out of the first project template for another subsidary. But then we have to change the network profile. Somebody has a clue how to solve this problem?
Best regards
Hi,
I managed to prototype your scenario successfully. Please follow below steps and let me know if there is any issue:
1. Create new project by copying old project without any network or activities. You can disable this in selection while copying old project.
2. Change network profile as required in new project and save it
3. Create network in new project by copying old project networks using Right Click on WBS>Create>Copy network function in CJ20N.
The new network will have new network profile and parameters. Hope this helps
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think relationships wont be lost - When you copy network all dependent objects like activity, material, relationships should get copied.
Only issue may be mapping of activities to correct WBS.
Regards
Shrikant
Edited by: Shrikant Rakate on Feb 14, 2012 1:19 PM
Edited by: Shrikant Rakate on Feb 14, 2012 1:20 PM
Hi,
Network Profile inherits from the Project Template from which you are copying , hence not possible to change.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.