Hi QM experts,
I am creating stability study; there are 2 types of storage condition 1. Intermediate condition 2. Long term condition.
The time interval for Intermediate condition is 3,6,9,12 months Long term 2,5,8,10
When I assign the main package to inspection plan (CWBQM) it will allow only one maint.statergy
How can I assign this two different main .statergy to one inspection plan (one stab .study) for different storage condition .
I do not want to create 2 inspection plan for this 2 condition i.e Intermediate 3,6,9,12 months & Long term 2,5,8,10
How can I solve this problem
Regards
AAdi
A inspection plan for a storage condition-- > a strategy & a strategy can have multiple Packages.-->which specify the frequency in which the individual tests can be performed (for example, after 3, 6, 9, 12, 18 months, and so on).
In such an inspection plan, you assign a strategy to the inspection plan header. At the operation level, you assign the desired packages in the strategy to the inspection operation (that is, you specify the frequencies in which this operation will be tested). It is therefore possible to define different, operation-specific frequencies for the same storage condition.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.