Hi Solman profis,

I have questions about the transport requests in QGM.

My Solution Manager is 7.1.

I have a Solman project, in which I activated QGM and created a Change and created two transport requests (one workbench, one customizing) attached to it, .

I'm little bit confused by the concept.

My questions are:

1. Why I cannot see the transport requests that I created previously in the DEV system manually? If it's normal, for which reason is this designed like this? If it's not normal, how can I configure to see those requests?

2. What is the difference between the Change here in QGM and the Change in ChaRM?

3. In practice, how should the transport requests be created? By the developer in DEV systems, or by the responsibles in Solution Manager Workbench (Change Management Workbench)?

Thanks a lot!

Edited by: Charlie Red on Feb 13, 2012 12:08 PM

Edited by: Charlie Red on Feb 13, 2012 12:09 PM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Can somebody help on this?

Former Member
0 Kudos

For the 3rd question, I think TRs should be created in Change Management Workcenter, is it the correct process?