cancel
Showing results for 
Search instead for 
Did you mean: 

Control key PM02 and PM03

Former Member
0 Kudos

Hi Gurus,

I am littele bit confused with PM02 external operation from PM03.

By both control key i got PR but by PM03 PR ML81n happened,but PM02 PR neither MIGO/ML81N happened.

Then what is use of PM02 PR?? and in SPRO PM02 control key is having schedule ext operation and PM03 having service field..

what is feature of this field???Pls explain....

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

If you create an operation using control key PM02 a normal goods receipt of the resulting PO will act as the confirmation of the operation, a PM03 requires the creation or selection of a Service Package, this then requires a service entry sheet to

confirm the delivery, tx ML81N.

If you use a PM02 control key the system will create a free-text PR using the data that you entered.

The process flow is then PR->PO->GR->IR

With a PM03 control key you will see a new Servicessub-tab at operation level. Here you can enter multiple services of different UoM.

The process flow is then PR->PO->SES->IR

For more info/scenario please visit site http://www.sap-img.com/plant/difference-between-the-control-keys-pm02-pm03.htm

Hope the above info clears your doubt.

Thanks.

Former Member
0 Kudos

Superb..resloved...

Answers (0)